Who : Christakis, Catrin
When : 27.6.2008
Where : Casa7 construction site
Purpose : General update and issues
--------------------------------------------------------------------------------------------
- The 3 openings in my sealing
When they finished the concrete sealing on my floor they omitted 3 openings for drainpipes. After completion of the sealing I had to move my kitchen door. Subsequently the drainage pipes have to be moved into my storage room. Pafilia will seal the holes with concrete.
- Design element first floor
The moulds contain sufficient iron to support the concrete structure of the design element (The “Sail”)
- Axels kitchen - Downdraft ventilation
I reminded Christakis to leave an opening for the downdraft ventilation in the kitchen floor. He did remember and it is taken care off.
- Alarm Security System
I advised Christakis that we need another electrical conduit for the Alarm Security System
- Axels floor
I advised Christakis where Axel wants to install his Security Webcams. He will take care of it.
- Photovoltaic
We discussed that Axel and I are planning to install Photovoltaic on our roof. I asked Christakis to plan for electrical conduits for Photovoltaic.
- Electrical door opener / garden door opener
We discussed to build provisions for electrical door openers.
Next week the sealing on Axel´s floor will be filled with concrete. If all goes well, they may even apply the concrete to the pool.
I asked Christakis to keep a couple of the bigger cragged granite pieces. We like to use them as decorative pieces in the garden.